Tolling agreements for battery storage in Germany: what a fixed fee secures and what it costs
Under a tolling agreement, an offtaker pays the owner of a battery storage system a fixed fee and markets the system on its own account. This article calculates what that would have cost against the market revenues of 2023 to 2025, which clauses can reduce the fee and what applies if the offtaker fails. It also asks what a fixed fee means for the investment deduction and special depreciation under German tax law.
Jakob HubertPublished 13 November 2026~12 min read
A battery storage system has no statutory remuneration. It earns from price differences on the power market and from balancing power; how these markets work is explained in direct marketing explained. Usually a marketer operates the system commercially and keeps a share of the revenue. The market risk then stays with the owner.
A tolling agreement (Tolling-Vertrag) reverses this. An offtaker pays a fixed amount per megawatt and year and keeps whatever it earns on the market. The contract is also called a flexibility purchase agreement. For investors, what counts is what is fixed, for how long and at what price.
What does a tolling agreement cover?
It gives the offtaker the right to charge and discharge the storage system in return for a fee that does not depend on market revenue. The offtaker buys the charging power, sells the discharged power, offers balancing power and carries the deviations in its balancing group. The owner keeps the system ready for operation: maintenance, insurance, grid connection, land lease. German law has no contract type of its own for this. Depending on the design, elements of a lease (§§ 535, 581 BGB) sit next to services; this matters further down for insolvency and tax.
Three basic models distribute the market risk differently:
Marketing with a revenue share (merchant): the marketer keeps a share of the revenue, the rest goes to the owner. No base amount, full market upside.
Floor: the marketer commits to a minimum and receives a larger share of the revenue in return.
Tolling: fixed fee, no share of market revenue. There are also variants in which no right of use is transferred; only the difference between a reference revenue and a fixed amount is settled.
How common are tolling agreements in Germany?
Less common than reports about individual large contracts suggest. According to the PPA market analysis 2025 of Marktoffensive Erneuerbare Energien, offtake and marketing agreements for battery storage totalling 1,092 MW became known in Germany in 2025, after 524 MW the year before. Of these, 843 MW had no price hedge. Contracts with a price hedge came to 249 MW, mostly tolling, after 140 MW in 2024. That is 23 per cent of the volume.
Two details matter for investors. First, all contracts with a price hedge were concluded for stand-alone systems, none for storage at a solar park. Second, the 1,092 MW are spread over 25 agreements, so around 44 MW per contract on average. The analysis also names the reason for the growing share: more projects are built with a higher share of debt, and their lenders usually require the revenues to be hedged.
What fixed fee corresponds to the market revenues of recent years?
Measured on the day-ahead market, around 52,000 euros per megawatt and year for a 2-hour system, if you average 2023 to 2025 and assume a marketer's revenue share of 15 per cent. This is our calculation, not a market price: the system runs one cycle a day, charges in the two cheapest hours and discharges in the two most expensive, at 86 per cent efficiency. That gives gross revenues of 52,100 euros (2023), 61,800 euros (2024) and 69,200 euros (2025) per megawatt; the same calculation is behind the comparison in 2-hour or 4-hour battery: which storage duration pays off for investors.
An offtaker does not pay the average, because it takes the risk and wants to earn from it. The table therefore shows a fixed fee of 90 per cent of the average result. Next to it is a floor model with a minimum of 70 per cent of average gross revenue and an owner's share of 75 per cent. The last row is a hypothetical year with 30 per cent less revenue than 2025.
Euros per MW
Market
Floor
Fixed
2023
44,327
42,729
46,697
2024
52,543
46,361
46,697
2025
58,788
51,872
46,697
Stress year
41,152
42,729
46,697
Own calculation (scripts/tolling-model.mjs). 2-hour system, day-ahead prices from SMARD, one cycle a day, efficiency 86 %. Market: marketing with a revenue share, 85 % of gross revenue. Floor: 75 %, at least 42,729 euros. Fixed: fixed fee of 46,697 euros. Assumptions, not market prices. Figures in euros per MW and year, rounded.
The ranking flips with the market. In 2023 the fixed fee was ahead, in 2024 and 2025 the revenue share, in the stress year the fixed fee again. The floor would never have applied in the three real years and would have cost between 1,600 and 6,900 euros a year; it only pays off when gross revenue falls below around 50,300 euros. For a 4-hour system all figures are higher (fixed fee by the same logic around 79,200 euros), the pattern is the same.
Two limits of the calculation: it only knows the day-ahead market. An offtaker also trades intraday and offers balancing power; these revenues are priced into a real fee but are left out here on both sides. It also assumes perfect foresight. The level of the figures is therefore an order of magnitude; what holds is the relationship between the models.
What does predictability cost over the term?
Over the three years together around 15,600 euros per megawatt, if the fee is set at 90 per cent of the average. In 2023 the owner would have received around 2,400 euros more than with a revenue share, in 2024 around 5,800 euros less, in 2025 around 12,100 euros less. Break-even is at a gross revenue of around 54,900 euros. Whoever chooses a fixed fee is therefore selling the fluctuation: between the weakest and the strongest of the three years, the revenue share differed by around 14,500 euros per megawatt.
Then there is what the contract does not cover. A storage system runs longer than its first marketing contract. With 15 operating years and a 5 per cent discount rate, five contract years cover 42 per cent of the present value, seven years 56 per cent, ten years 74 per cent. For the rest the investor carries the market risk again, by then with an aged system. A revenue forecast that carries the fixed fee forward over the whole operating life is calculating with something that has not been agreed.
Which clauses decide whether the fee is really fixed?
Those on availability and capacity. The fee is paid for a system that actually provides the promised power and energy. If it falls short, the fee is reduced; by how much differs from contract to contract. For scale, again using 46,700 euros per megawatt and year:
Availability: with a pro-rata reduction, each percentage point below the commitment costs around 470 euros a year. A 14-day outage is 3.8 per cent of the year, so around 1,800 euros. The points to clarify are whether the reduction is pro rata or steeper and whether the offtaker may terminate above a threshold.
Capacity: if the fee is tied to usable energy and the system ages by 2.5 per cent a year, 86 per cent is left in year seven. Over seven years that adds up to around 23,500 euros, half an annual fee. The alternative is augmentation at the owner's expense. What capacity warranties cover is explained in The battery as a real asset: lifespan, degradation and warranties of a grid-scale storage system.
Cycles and dispatch: the offtaker earns from every cycle, the owner bears the ageing. The number of cycles in the contract has to match the manufacturer's warranty. Otherwise a dispatch pattern the owner does not control can cost the warranty cover.
Efficiency: if the owner commits to an efficiency level, it is liable for losses beyond that.
For many systems it is also open who bears future burdens. Charging power is exempt from grid fees for 20 years for systems commissioned by 4 August 2029 (§ 118 para. 6 EnWG); what applies afterwards is being reorganised, see Grid fees for battery storage: the exemption until 2029 and the AgNeS reform. The capacity market adds a possible new income (German capacity market: what does it offer battery storage and solar parks?). Grid operators may also instruct storage systems of 100 kilowatts and above in redispatch (§ 13a para. 1 EnWG). A contract running seven or ten years should say who bears new charges, who is entitled to new revenues and whether the fee continues when the grid operator intervenes.
Clause
What to look for
Fee
based on MW or usable MWh, indexation
Availability
commitment, reduction rule, threshold for termination
Capacity, cycles
ageing, augmentation, cycle count against the manufacturer's warranty
Change in law
grid fees, capacity market, redispatch
Term, end
extension, condition on return, transfer on sale
Payment, security
payment in advance, guarantee, termination on default
Own compilation. Not legal advice.
What does a tolling agreement change for financing?
It makes debt service predictable; that is usually why it is concluded. Our example: of the fixed fee of 46,700 euros, around 25,900 euros per megawatt remain after fixed operating costs of 20,700 euros. If a bank requires this surplus to cover debt service 1.2 times (an assumption), it supports around 21,600 euros of interest and repayment a year. At 5.5 per cent interest and a seven-year term, that corresponds to a loan of around 123,000 euros per megawatt. With a revenue share, the same debt service would have been covered less evenly:
Cover
Fixed
Market
2023
1.20
1.09
2024
1.20
1.47
2025
1.20
1.76
Stress year
1.20
0.94
Own calculation (scripts/tolling-model.mjs). Debt service 21,624 euros per MW and year, fixed operating costs 20,749 euros (30 % of gross revenue 2025). Cover = surplus divided by debt service. Fixed: fixed fee. Market: marketing with a revenue share. Assumptions, not bank terms.
In the stress year the surplus under a revenue share no longer covers the instalment. Then there is the distribution within the year: in our calculation, December 2025 brought 3.6 per cent of annual revenue and June 12.0 per cent; the three weakest months together brought 13 per cent instead of a quarter. A fixed fee flows evenly. The market analysis names this link as the reason for the growing share of contracts with a price hedge. What else a bank wants to see is covered in Financing a direct investment: bank loan, KfW 270 and the pitfalls.
What happens if the offtaker does not pay or becomes insolvent?
Then there is no statutory bridge like the fallback tariff for a solar park. The storage system only earns again once someone else markets it. For that, the old contract has to be ended. Until then, whatever has been provided and not yet paid is outstanding. With monthly payment in arrears and a one-month payment term that is two monthly fees, in the example around 7,800 euros per megawatt; with quarterly settlement four months, around 15,600 euros. For a 5 MW system that is just under 78,000 euros.
In insolvency proceedings the administrator chooses whether to perform the contract (§ 103 InsO). If performance is chosen, the fee for the period after the opening has to be paid from the estate (§ 55 para. 1 no. 2 InsO); arrears from before are insolvency claims. The statutory continuation of leases applies only to immovable property and premises (§ 108 para. 1 sentence 1 InsO), so it does not help for a storage system as a movable asset. A clause that ends the contract as soon as insolvency is filed is generally invalid when it favours the party that is owed money (§ 119 InsO; Federal Court of Justice, judgment of 27 October 2022, IX ZR 213/21). The reasoning is set out in the article on the direct marketing contract.
For a fixed fee, § 112 InsO comes on top. If the contract is classified as a lease, the owner may no longer terminate after the insolvency filing because of a payment default that occurred before the filing. The offtaker's deteriorated financial position is not a ground for termination either. Whether a tolling agreement falls under this depends on its design; we are not aware of a decision by the highest courts. In practice this means a termination right for payment default has to take effect before the offtaker files.
Three things can protect the owner: payment in advance or at short intervals, security from the offtaker (a bank guarantee or parent company guarantee covering several monthly fees) and a rule on how the system returns to the owner technically and in the balancing group. The general framework is described in Provider or operator insolvency: what happens to your direct investment.
Does a fixed fee change the tax classification?
It can. The investment deduction (Investitionsabzugsbetrag) and special depreciation require a business that determines its profit under § 4 or § 5 EStG (§ 7g para. 1 sentence 2 no. 1 EStG). Handing the system over to a third party does no harm in itself: since the Annual Tax Act 2020, § 7g expressly covers leased-out assets as well. The tax authorities treat use by others for a fee as business use if the rent is recorded as business income (Federal Ministry of Finance circular of 15 June 2022, para. 36).
The question sits one step earlier: is there a commercial business at all? Under the income tax guidelines, letting movable assets in principle leads to other income under § 22 no. 3 EStG. It becomes commercial when significant additional services are provided or the scale requires a business organisation (R 15.7 para. 3 EStR). With other income there would be no investment deduction; losses could not be offset against other income (§ 22 no. 3 sentence 3 EStG).
So the roles in the contract matter. If the investor remains the operator who commits to availability, arranges maintenance and insurance and holds the grid connection, that points to a commercial business with a fixed rather than a fluctuating revenue. If the investor hands the system over completely and only receives a rent, it resembles the lease model we describe as risky for tenant electricity systems. For tolling agreements on battery storage we know of neither a court ruling nor an administrative instruction. Anyone who wants certainty clarifies the classification with a tax adviser before investing, and for larger amounts through a binding ruling from the tax office (§ 89 para. 2 AO). The other requirements of the deduction are covered in IAB under §7g EStG: example calculation for battery storage.
Does a storage system of a few megawatts get a tolling agreement at all?
As a single contract rather rarely, as far as the published figures show. The agreements that became known in 2025 averaged around 44 MW; according to the market analysis, the offtakers of contracts with a price hedge were mainly utilities. Technical review, contract negotiation and security cost about as much for 2 MW as for 100 MW. There is no statistic on small systems; the statement is an inference from the averages.
For a direct investment in the single-digit megawatt range, three routes are therefore more realistic: marketing with a revenue share, a floor or a framework contract that the project developer concludes for many systems together. With the third route it matters that the contract is disclosed and transfers to the investor with the system. If the revenue forecast for a small system shows a fixed fee, the contract should be on the table: signed, with offtaker, term and security. How stand-alone systems and storage at a solar park otherwise differ is shown in Co-located vs. stand-alone: which gives the better risk structure.
Which questions should you ask the provider about the marketing contract?
Is there a signed contract or only a letter of intent? Who is the offtaker?
What exactly is fixed: a fee per MW or per MWh of usable capacity? Is it indexed?
Which availability is committed, how is the fee reduced and from when may the offtaker terminate?
How many cycles may the offtaker run? Does that match the manufacturer's warranty?
When is payment made, what security does the offtaker provide and what applies on payment default?
Who bears new grid fees and interventions by the grid operator? Who is entitled to revenues from the capacity market?
How long does the contract run? What does the revenue forecast assume afterwards?
Do I remain the operator of a commercial business for tax purposes? Has a tax adviser reviewed the contract for this?
How we assess marketing contracts for storage in project review
We ask for the contract before the reservation and compare it with the revenue forecast: same model, same term, same deductions. With a fixed fee we check how long it applies, what the forecast assumes for the years after, what security the offtaker provides and whether the cycle count matches the manufacturer's warranty. With a revenue share we run a weak year against debt service. In both cases we look at the roles in the contract with the investment deduction in mind and refer you to your tax adviser for the classification. The further risks a storage system carries are collected in Risks in BESS direct investments, and how they are structurally addressed. That is exactly what we review in a no-obligation initial consultation. We do not give return guarantees.
Frequently asked questions
What is a tolling agreement for battery storage?
A contract in which the owner gives an offtaker the right to charge and discharge the storage system. The offtaker pays a fixed fee per megawatt and year and markets the system on its own account. The owner keeps the system ready for operation and bears maintenance, insurance and ageing.
What is the difference between tolling, a floor and marketing with a revenue share?
The distribution of market risk. With a revenue share the marketer keeps a share and the owner carries the market risk. With a floor the marketer commits to a minimum and receives a larger share in return. With tolling the owner receives a fixed amount and nothing from market revenue.
How high is the fee in a tolling agreement?
It is freely negotiated and not published; there is no official statistic. In our calculation, the result of a 2-hour system on the day-ahead market in 2023 to 2025, after a marketer's share of 15 per cent, averaged around 52,000 euros per megawatt and year. A real fee also reflects intraday trading and balancing power, and a discount for the offtaker's risk.
How long does a tolling agreement run?
The term is freely negotiated. With 15 operating years and a 5 per cent discount rate, five contract years cover 42 per cent of the present value, seven years 56 per cent, ten years 74 per cent. After that the storage system is back in the market.
Who bears availability and ageing of the storage system?
The owner. If the system falls short of the committed availability or capacity, the fee is reduced. In our example one percentage point of availability costs around 470 euros per megawatt and year; ageing of 2.5 per cent a year adds up to around half an annual fee over seven years if the fee is tied to usable capacity.
What happens if the offtaker becomes insolvent?
The insolvency administrator decides whether to perform the contract (§ 103 InsO). Arrears from before the opening are insolvency claims. If the contract is a lease, the owner may no longer terminate after the filing because of older arrears (§ 112 InsO). This is why payment at short intervals and security from the offtaker matter.
Is the investment deduction available with a tolling agreement?
§ 7g EStG also covers leased-out assets but requires a business that determines its profit. If the investor remains the operator with duties of its own, that points to a commercial business. With a pure handover against rent, the tax authorities may assume other income. This has not been decided for storage; the classification belongs with a tax adviser before investing.
Is a tolling agreement worthwhile for a small storage system?
The agreements that became known in Germany in 2025 averaged around 44 MW; all contracts with a price hedge concerned stand-alone systems. For systems of a few megawatts, a revenue share, a floor or a developer's framework contract is the more usual route. If a fixed fee appears in the forecast, the contract should be on the table.