Copernica Partners
Back to Insights
Markets & technology

A solar park after 20 years: continued operation, repowering or decommissioning?

The 20 years of EEG remuneration are the best-known date in the life of a solar park, but not its end. The modules keep producing, the grid connection keeps its value, and what becomes of the site is decided by the land lease. This article sorts out the four different lifetimes of an energy direct investment, walks through the three paths at the end of the subsidy period and explains how residual value and decommissioning costs belong in an honest return calculation.

Jakob HubertJakob HubertPublished 23 August 2026~10 min read

Anyone reviewing a direct investment in a solar park or battery storage facility soon runs into the number 20: 20 years of EEG remuneration, a 20-year tax depreciation period for photovoltaics, often a 20-year financial model. From there it is a short step to the mistaken idea that everything stops after 20 years. In reality, several clocks run in parallel in a solar park, and they stop at different times. Keeping those clocks apart makes project calculations far easier to judge: what is secured, what is an assumption, and what is a hidden reserve?

How long does a solar park really run?

Longer than 20 years. The 20 years are a subsidy and tax deadline, not a technical one. In a project calculation, four different clocks are running, and they should not be confused: tax depreciation, the subsidy or privilege window, technical lifetime, and the contract terms of the land lease and the participation itself.

LevelSolar park (PV)Battery storage (BESS)
Tax depreciation period20 years per the official depreciation table10 years per the official depreciation table
Subsidy or privilegeEEG payments for 20 years plus the rest of the commissioning year (Sec. 25 EEG)No EEG remuneration; grid-fee exemption for charging power for 20 years from commissioning (Sec. 118 (6) EnWG)
TechnologyModules with performance warranties over 25 to 30 years; inverters usually do not last that long and are replaced during operationCells designed for 15 to 20 operating years; capacity can be topped up through augmentation
ContractsLease and participation terms typically 20 to 30 years, often with extension optionsParticipation and model horizons typically 15 to 20 years
Four lifetime levels compared: solar park (PV) and battery storage (BESS)

The technical clock runs longest. Wafer-based solar modules age slowly: a Fraunhofer ISE measurement series across 44 quality-assured plants in Germany found an average degradation of nominal power of around 0.15 percent per year, while a broad NREL review of almost 2,000 published measurements puts the median at 0.5 percent per year. Sound calculations use the more conservative figure. Even then, a module still delivers close to 90 percent of its initial output after 25 years, and manufacturers typically warrant no more than 10 to 15 percent performance loss over 25 to 30 years. Battery storage ages faster and depends far more on how it is operated; how degradation, warranties and augmentation work there is covered in The battery as a real asset: lifespan, degradation and warranties of a grid-scale storage system.

What ends after 20 years, and what continues?

The subsidy ends, not the operation. Under Sec. 25 of the German Renewable Energy Sources Act (EEG), market premiums and feed-in payments run for 20 years; for plants with a statutory applicable value the period extends to 31 December of the twentieth year. After that, the payment claim expires and nothing else: the plant remains permitted, the grid connection stays in place, and the electricity may still be sold, just without a state-secured minimum price.

For small installations the legislator created a transitional solution: so-called post-subsidy installations still receive a follow-on feed-in payment until the end of 2032. Under the statutory definition, however, only installations up to 100 kilowatts qualify (Sec. 3 no. 3a EEG), which means the typical rooftop system. A megawatt-scale solar park does not fall under it. After the subsidy ends it moves into merchant marketing under Sec. 21a EEG: the electricity is sold on the exchange via a direct marketer or secured through a power purchase agreement; how such contracts are built is explained in Understanding PPAs: how power purchase agreements make solar park revenues predictable.

For battery storage the question presents itself differently, because it lives on market revenues rather than EEG payments from day one. Its most important privilege is the exemption of charging power from grid fees, and that too is designed to run for 20 years from commissioning (Sec. 118 (6) EnWG). Since the cells are designed for 15 to 20 operating years, this window covers the usual analysis period; it only becomes critical for models that reach well beyond it. The details are in Grid fees for battery storage: the exemption until 2029 and the AgNeS reform.

What are the three paths at the end of the subsidy period?

Continued operation, repowering or decommissioning. Which path wins economically depends on the condition of the plant, on power prices and above all on what the land lease and the permit allow.

Continued operationRepoweringDecommissioning
What happensThe plant keeps running unchanged, power is sold on the marketModules (and usually inverters) are replaced with current technology; site and grid connection remainThe plant is dismantled, the site cleared and handed back
Capital requiredLow; running costs and occasional repairsHigh; essentially a new investment on developed landDecommissioning costs, partly offset by material proceeds
Revenue baseMarket value of solar power or PPA prices, no subsidyDepending on the route, a new EEG auction award or a PPA at new-build termsNone; only recovery proceeds from metals and components
Typical triggerPlant technically fit, low operating costs, acceptable power pricesOld plant uses land and grid connection poorlyLease ends, permit lapses or continued operation is uneconomic
The three options at the end of EEG support at a glance

In practice this is not a decision taken in year 20 but a gradual process: operators keep comparing whether the next major repair (say, an inverter replacement) is still worth investing into continued operation or becomes the occasion for repowering. For investors in a direct participation, the point is less which path the model assumes and more whether the provider keeps all three open.

What does repowering mean in practice?

Repowering means the plant technology is replaced with current equipment while the site stays. The value lies less in the old modules than in what exists around them: secured land, a grid connection with feed-in capacity, access rights, an established operation. Because modern modules deliver considerably more output per square metre than the technology of 20 years ago, significantly more capacity can be installed on the same site; the grid connection, the scarcest factor in many regions, is already there.

Two points are often misunderstood. First, swapping modules does not automatically trigger a new subsidy: under Sec. 3 no. 30 EEG, replacing the generator or other technical components does not change the plant's commissioning date. New EEG remuneration is only available through the regular route, meaning a new award in the auctions or a power purchase agreement at new-build terms. Second, the permitting situation is not trivial: whether repowering counts as a mere modification or needs a new procedure is not regulated uniformly in German building law; a 2025 study commissioned by the Federal Environment Agency explicitly calls for clearer administrative rules. A provider who prices repowering in as a certain value should be able to answer both points.

For tax purposes, repowering is at its core a new investment: the new components are capitalised and depreciated over their useful life, and under the conditions of Sec. 7g of the German Income Tax Act a new investment deduction amount may come into play. How that mechanism works is explained in The Investitionsabzugsbetrag explained simply: how the IAB works; the specifics belong with your tax advisor.

Who pays for decommissioning, and what is left of the site?

The operator pays, and the site becomes free again. For solar parks permitted as privileged projects in undesignated outlying areas (for instance along motorways and railways or as agrivoltaics under Sec. 35 (1) no. 8b and no. 9 of the German Federal Building Code), the law already requires, as a condition of the permit, a binding declaration to dismantle the installation after final abandonment of use and to remove soil sealing (Sec. 35 (5) sentence 2 BauGB); the authority is to secure compliance, for instance through a land charge. Most large ground-mounted parks, however, are built on the basis of a municipal development plan. There the decommissioning duty is regularly anchored in an urban development contract under Sec. 11 BauGB and backed by security, usually a bank guarantee whose amount the municipality sets.

How high decommissioning costs will actually be cannot be put into euros credibly today; even the study commissioned by the Federal Environment Agency recommends first creating a standardised expert basis so that security amounts can be determined consistently nationwide. Two things can be said, though. First, a solar park is not hazardous waste but mostly a store of raw materials: steel, aluminium, copper and glass whose recovery finances part of the decommissioning. Second, disposal of the modules is regulated: under the German Electrical and Electronic Equipment Act they count as large equipment, manufacturers must take them back, and their category is subject to minimum quotas of 85 percent recovery and 80 percent recycling (Sec. 22 ElektroG). For battery storage, the EU Battery Regulation sets its own rising recovery quotas; what happens at the end of a storage system's life is described in The battery as a real asset: lifespan, degradation and warranties of a grid-scale storage system.

For judging a project, the structure therefore matters more than the exact cost figure: is a decommissioning obligation fixed contractually, is it backed by sufficient security, and does decommissioning appear as a cost item in the calculation? A model that simply stops at zero at the end of the term has a gap.

Why is the land lease the real lever?

Because it decides who owns the options after year 20. Continued operation and repowering both require the site to be secured beyond the end of the subsidy. If the lease ends after 20 years, the operator negotiates at the worst possible moment: the landowner knows that the grid connection and infrastructure are tied to this site, and can price that in. This is why site agreements for solar parks are usually concluded beyond the subsidy period, often with staggered extension options reaching 30 years and more.

German civil law sets a little-known limit here: a lease concluded for longer than 30 years can be terminated extraordinarily by either party after 30 years have elapsed (Sec. 544 of the German Civil Code, applied to leases via Sec. 581 (2)). Very long fixed terms are therefore worth less than they sound; more robust is a base term with extension options plus security in the land register, typically a restricted personal easement that preserves the right of use even if the land changes owner. Well-negotiated contracts also state explicitly whether repowering is covered by the lease and how decommissioning is handled at the end.

How does residual value belong in the return calculation?

Conservatively or not at all. After the subsidy ends, revenues come from the market value of solar power, published monthly by the transmission system operators, or from follow-on PPAs; neither can be forecast credibly two decades in advance, especially as growing solar volumes depress market values in sunny hours. How this already shows up in hours of negative prices is described in Negative electricity prices: what they mean for solar and storage investors. A robust calculation therefore lets the participation pay off within the secured subsidy period and treats the years after that as upside with cautious price assumptions, not as a load-bearing pillar of the return.

Residual value also has a second, tax-related twist: once depreciation is exhausted, hardly any book value stands against the proceeds. If the plant or the participation is sold at that point, the sale price is essentially taxable profit; the mechanics are explained in After the IAB: How the ongoing returns and the sale of a direct investment are taxed. The residual value also plays a role in the profit-intent test, because the total-profit forecast needs a plausible end-of-term recovery scenario; details are in Liebhaberei and profit intention: when the tax office cancels the tax lever. Those who do not want to hold until the end of the term will find the exit routes in Selling a direct investment early: how liquid an energy direct investment really is.

Which questions should you put to any provider?

How a provider handles the end of the term says a lot about the quality of a project. These questions belong in every conversation:

  • How long does the land lease run, which extension options exist, and is the right of use secured through an easement in the land register?
  • Does the lease explicitly cover a later repowering?
  • What residual value and which revenue assumptions does the model use after EEG remuneration ends?
  • Does the participation still pay off if the years after the subsidy are set to zero?
  • What decommissioning obligation exists, how much security backs it, and is decommissioning a cost item in the model?
  • Which inverter replacement cycles and other reinvestments are planned?
  • For storage: how far does the grid-fee exemption under Sec. 118 (6) EnWG reach relative to the model horizon, and is augmentation planned?
  • Which degradation assumption is used in the yield report, and is it more conservative than the manufacturer's warranty? How to read such a report as a whole is shown in Reading a yield assessment: what P50 and P90 mean for a solar park direct investment.
  • Who looks after the plant in year 15 and in year 25, and what does that cost?

How we check end-of-term and residual value in our project review

We review every project before presenting it to investors, and the end of the term is a review block of its own: lease term and options relative to the model horizon, security in the land register, decommissioning arrangements and their backing, reinvestment assumptions for inverters and equipment, and the question of whether the return holds up without residual-value fantasy. What generally distinguishes a diligent provider is summarised in How to tell a trustworthy provider of energy direct investments; what ongoing support looks like over the decades after signing is shown in What happens after closing: reporting, asset management and why a partner is not a broker. If you have a specific offer on the table or want to see what an end-of-term check looks like in practice, talk to us in a no-obligation initial consultation. We do not make return promises.


Frequently asked questions

Does a solar park have to be dismantled after 20 years?

No. After 20 years the EEG remuneration ends, not the operating permit. The plant may keep running and sell its electricity through direct marketing or power purchase agreements. Decommissioning only falls due once use is finally abandoned, the lease ends or continued operation becomes uneconomic; the decommissioning duty itself follows from the permit or the urban development contract.

What happens to the EEG remuneration after 20 years?

The claim ends. Sec. 25 EEG grants the market premium or feed-in payment for 20 years, extended to 31 December of the twentieth year. A follow-on payment until the end of 2032 exists only for so-called post-subsidy installations up to 100 kilowatts, so not for solar parks. These market their electricity afterwards through merchant marketing under Sec. 21a EEG or via a PPA; how that works is explained in Understanding PPAs: how power purchase agreements make solar park revenues predictable.

What is repowering in photovoltaics?

Replacing the plant technology with current equipment while keeping the site. Because modern modules deliver considerably more output per area, significantly more capacity can be installed on the same site with the same grid connection. Economically, repowering is a new investment on already developed land; for tax purposes, depreciation starts afresh for the new components.

Does a repowered solar park automatically receive new EEG support?

No. Under Sec. 3 no. 30 EEG, replacing modules or other technical components does not change the plant's commissioning date; the old subsidy neither revives nor restarts. New remuneration is only available through the regular route via the EEG auctions or through a power purchase agreement at new-build terms.

Who pays for the decommissioning of a solar park?

The operator. For privileged projects in outlying areas, Sec. 35 (5) BauGB already requires a binding decommissioning declaration, including removal of soil sealing, as a condition of the permit; for parks based on a development plan, the duty is set out in an urban development contract under Sec. 11 BauGB and usually backed by a bank guarantee. Material proceeds from steel, aluminium, copper and glass cover part of the costs; manufacturers must take modules back under the ElektroG.

How long do solar modules really last?

Considerably longer than the subsidy period. Measured degradation rates range from around 0.15 percent per year (Fraunhofer ISE) to a median of 0.5 percent per year in a broad NREL review; manufacturers typically warrant no more than 10 to 15 percent performance loss over 25 to 30 years. Even with the conservative assumption, a module still delivers close to 90 percent of its initial output after 25 years. Inverters last less long and are replaced in the course of operation.

How long should the land lease of a solar park run?

Longer than the subsidy, otherwise the options after year 20 belong to the landowner. Base terms with extension options reaching 30 years and more, plus security in the land register, are customary. Note Sec. 544 of the German Civil Code: contracts of more than 30 years can be terminated by either party after 30 years, which is why option structures are more robust than extremely long fixed terms.

What applies to battery storage after 20 years?

The clocks run faster for storage: cells are designed for 15 to 20 operating years, tax depreciation runs over 10 years, and the grid-fee exemption for charging power under Sec. 118 (6) EnWG applies for 20 years from commissioning. Operating far beyond that is rarely the scenario; instead, augmentation during the term and recycling and second life at the end are what matters, as described in The battery as a real asset: lifespan, degradation and warranties of a grid-scale storage system.

Sources

  1. Sec. 25 EEG: start and duration of the claim (gesetze-im-internet.de)
  2. Sec. 3 EEG: definitions, incl. post-subsidy installations and commissioning (gesetze-im-internet.de)
  3. Sec. 21a EEG: merchant direct marketing (gesetze-im-internet.de)
  4. Sec. 35 BauGB: building in outlying areas, decommissioning obligation (gesetze-im-internet.de)
  5. Sec. 11 BauGB: urban development contract (gesetze-im-internet.de)
  6. Sec. 544 BGB: contracts for more than 30 years (gesetze-im-internet.de)
  7. Sec. 118 (6) EnWG: grid-fee exemption for storage (gesetze-im-internet.de)
  8. Sec. 22 ElektroG: recovery quotas; PV modules as large equipment (gesetze-im-internet.de)
  9. Fraunhofer ISE: Recent Facts about Photovoltaics in Germany (ise.fraunhofer.de)
  10. Jordan/Kurtz (NREL): Photovoltaic Degradation Rates, an Analytical Review (Progress in Photovoltaics, 2013)
  11. German Federal Environment Agency: legal questions on decommissioning obligations and repowering of ground-mounted PV (Climate Change 43/2025)
  12. Transmission system operators: market value overview (netztransparenz.de)

Personal first conversation

Less reading: a short call.

30 minutes, free and without obligation. We understand your tax situation and show which project structures fit you, or whether today is (not yet) the right moment.

Learn more