Agrivoltaics with livestock from an investor's perspective: when sheep, cattle and hens turn a solar park into a special solar installation

Sheep under the module tables, cattle between vertical module rows, laying hens in the shade of the modules: solar parks with animals are offered more often. Whether such a park counts as agrivoltaics under the German EEG depends on the land, on the design and on evidence every three years. This article sets out what the law requires, what the animal-friendly design costs per kilowatt and per hectare, and what the surcharge depends on during operation.

Jakob HubertJakob HubertPublished 12 November 2026~14 min read

Sheep keeping a solar park short has been common practice for years. What is newer is livestock as part of the plant concept: cattle graze between tall or vertical module rows, laying hens use the modules in their range as protection from birds of prey and sun. Since June 2024 there has been a dedicated technical rule for this, DIN SPEC 91492.

For investors there is a question behind this that affects the business case: is this an ordinary solar park with animals as vegetation management, or a special solar installation (besondere Solaranlage) within the meaning of the EEG? In the first case the animals change nothing about revenue. In the second there is access to grassland and, for some designs, a surcharge. In return the hectare carries less capacity, the frame costs more and the support depends on evidence that the livestock farmer has to supply. We do not currently offer an agrivoltaics project with livestock; this article is an assessment of the concept.

Is a solar park with sheep already agrivoltaics?

No. In a solar park with sheep, grazing is as a rule vegetation management. The plant is an ordinary ground-mounted plant, bids in the tender on one of the usual site categories and receives the award value without a surcharge. The EEG mentions grazing there only as one of five nature conservation criteria, of which a park must meet at least three: a maintenance concept with no more than two cuts a year or strip grazing with an adapted stocking density (§ 37 (1a) no. 2 EEG). Which land an ordinary park may use is set out in Eligible land: where can a solar park be built in Germany?.

Agrivoltaics within the meaning of the EEG is a special solar installation where farming continues on the same land. For grazing animals one category is relevant: grassland that is not peat soil, with simultaneous use as permanent grassland (§ 37 (1) no. 3 (c) EEG). The difference from an ordinary park shows in three places.

  • Land: a special solar installation may stand on permanent grassland that is open to an ordinary park only through the general categories, for example in a less-favoured area or along motorways and railways. Peat soils, Natura 2000 sites and protected habitat types remain excluded.
  • Remuneration: the award value comes from the same tender as for any other park. A surcharge exists only for certain designs.
  • Obligations: farming must continue over the entire support period and is confirmed by an expert every three years.

Whether the information memorandum says agrivoltaics, pasture PV or solar park with grazing tells you nothing about this. What matters is the site category in which the plant received its award. The general classification of agrivoltaics is set out in Investing in agrivoltaics: dual land use, revenues and tax leverage at a glance.

What does the EEG require of an agrivoltaics plant on grassland?

That the land is permanent grassland (Dauergrünland) and continues to be farmed as such. The Bundesnetzagentur set the requirements in a determination (Festlegung) of 1 July 2023. Permanent grassland is land on which grass or other herbaceous forage grows and which has not been part of the crop rotation for at least five years; permanent pasture is included. Farming must be taking place at commissioning and must not be significantly restricted by the solar plant in intensity, type, duration or timing. Four points of the determination matter for projects with animals.

  • Mowing or grazing: both are permitted. Switching from grazing to mowing and from intensive to extensive use also remains allowed.
  • No switch from arable land to grassland: arable land sown with grass for the construction of the plant is not permanent grassland within the meaning of the determination. The five years must lie before commissioning.
  • Species: if a particular species grazed the land before construction, grazing with that species must remain possible. The expert report at commissioning confirms that the grazing planned in the farming concept is possible.
  • Evidence: an expert report on the state of the art at commissioning, then in every third year an expert confirmation that the grassland was farmed over the past three years. Aerial images, photographs, payment records from farm subsidies or extracts from the field record (Schlagkartei) are sufficient. Nobody has to prove a particular yield level.

The authority expressly rejected requirements on grazing management, such as periods without animals. Nor does the land have to be in the farm subsidy scheme. What is required is actual continuation: according to the reasoning, farming and solar plant form an inseparable unit. Plants above one megawatt bid in the tender for first-segment solar plants; smaller ones receive the statutory value under § 48 (1) sentence 1 no. 5 (c) EEG.

Which standard counts: DIN SPEC 91434 or DIN SPEC 91492?

For the EEG, the older one. The determination refers statically to DIN SPEC 91434 in its May 2021 version. It describes agrivoltaics in general and lists permanent grassland with grazing as a category of its own without elaborating on it. DIN SPEC 91492 of June 2024 fills that gap for livestock. The Bundesnetzagentur could not include it in 2023 because it had not yet been adopted. In its notes on the bid date of 1 December 2026 the authority does not name a newer determination for grassland.

The new standard is useful all the same, because it names what matters with animals.

  • Two categories: high-mounted from 2.10 metres of clearance, where the animals use the land under and between the modules, and ground-level or vertical.
  • Loss of land of no more than 15 per cent of the project area. Permanently installed fences without an agricultural function count towards it, mobile pasture fences do not.
  • Stocking of at least 85 per cent of a reference area. Less is permitted if the farming concept justifies an improvement, for example in animal welfare.
  • Protection in both directions: animals must not injure themselves on the plant. Cables and frame must be secured against chewing, biting and rubbing.
  • An agricultural use concept signed jointly by farmer and operator, with a use plan for the first three years.

For investors this means: planning to DIN SPEC 91492 is a quality feature for the interaction of animal and technology. It does not secure the status as a special solar installation. That depends on the grassland definition of the determination and on DIN SPEC 91434, to which the farm subsidy rules also refer.

What does a hectare earn depending on the design?

Considerably less electricity than an ordinary park, because more space remains between the modules. We calculated three designs at the same site in central Germany, with hourly profiles from PVGIS and the exchange prices of 2025: the ordinary park with 1,000 kilowatts per hectare, a high-mounted plant with 600 kilowatts and vertical bifacial module rows with 250 kilowatts per hectare. The densities follow assumptions by Fraunhofer ISE for ground-mounted plants, high-mounted plants and vertical modules.

DesignkWp per haRevenue per kWpRevenue per ha
Vertical bifacial250€66.1€16,500
High-mounted600€55.5€33,300
Ordinary park1,000€52.7€52,700
Own calculation (scripts/tierhaltung-pv-model.mjs): PVGIS 5.3, site 51.0° N / 10.0° E, weather year 2023, 14 % system losses; day-ahead prices 2025 (SMARD); reference value 4.79 ct/kWh (volume-weighted award 01.07.2026), for high-mounted plus 0.5 ct surcharge; market premium against the 2025 annual solar market value of 4.508 ct/kWh; no payment in negative-price hours. High-mounted fixed south 20°, ordinary park fixed south 25°, vertical with east and west faces and a bifaciality factor of 0.9. Annual yields 984, 997 and 1,011 kWh per kWp. Without row shading, degradation, marketing fee, lease and operating costs.

Per hectare the high-mounted plant reaches 63 per cent and the vertical one 31 per cent of the electricity revenue of an ordinary park. Per kilowatt the picture is different. Vertical modules generate in the morning and evening, when electricity is worth more: only 17 per cent of their generation fell into hours with a negative price in our calculation, against 25 per cent for the south-facing plants. Their revenue per kilowatt was therefore around a quarter higher. The calculation contains no shading between rows and assumes that the rear side delivers 90 per cent of the front. Both assumptions favour the vertical plant. How orientation affects revenue is covered in detail in South, east-west or vertical: which solar park layout pays off for investors.

The low density has a price that does not appear in comparisons per kilowatt: the land. For every 1,000 euros of lease per hectare and year, one kilowatt carries 1.00 euro in the ordinary park, 1.67 euros high-mounted and 4.00 euros vertical. For the vertical plant that is 6 per cent of annual revenue, for the ordinary park just under 2 per cent. An agrivoltaics lease therefore has to be well below that of an ordinary park per hectare. In return the lessor keeps the farming. What should be in the lease is described in The land lease of a solar park from the investor's side: why it is a Mietvertrag, what the rent costs per kilowatt and how you step into the contract.

Does the agrivoltaics surcharge cover the extra cost?

For high-mounted plants it does not. The surcharge of 0.5 cents per kilowatt hour goes today only to special solar installations that are, in the wording of the law, horizontally mounted; the Bundesnetzagentur speaks of high-mounted agrivoltaics, meaning a clearance from 2.10 metres. It applies to awards in the years 2026 to 2028. Vertical and ground-level plants do not receive it. The rule comes from the May 2024 version of the EEG, because the more generous provisions of the Solarpaket I were never applied for lack of approval by the European Commission (§ 101 (1) EEG). According to the Bundesnetzagentur's notes this also holds for the bid date of 1 December 2026 as long as the approval is missing.

The tall frame costs more. Fraunhofer ISE puts the substructure of high-mounted plants below four metres at 243 to 306 euros per kilowatt against 76 euros for a ground-mounted plant, and site preparation and installation at 137 against 67 to 100 euros. Together that is 221 to 284 euros of extra cost per kilowatt. For ground-level systems, among which we count the vertical ones, it gives 97 to 167 euros for the substructure and 93 euros for installation, that is 31 to 101 euros more than for a ground-mounted plant. The energy agency of Rhineland-Palatinate arrives at 600 to 800 euros per kilowatt for a plant mounted two metres high with livestock, against 450 to 600 euros for a ground-mounted plant. That confirms the order of magnitude for the tall frame. For vertical systems it gives around 700 euros, more than the Fraunhofer ISE range suggests.

DesignExtra costSurcharge covers
Vertical (2027 draft)€31 to €10151 to 167 %
High-mounted€221 to €28416 to 21 %
Own calculation (scripts/tierhaltung-pv-model.mjs): extra cost for substructure, site preparation and installation against a ground-mounted plant according to Fraunhofer ISE, agrivoltaics guideline, June 2025, p. 45. Figures per kWp. Surcharge of 0.5 ct/kWh on the remunerated volume, 20 years, discounted at 5 %: present value €51 per kWp (vertical) and €46 per kWp (high-mounted). For vertical plants the surcharge exists only under the EEG 2027 draft.

The surcharge brings the high-mounted plant 3.72 euros per kilowatt and year, because it is paid only on the kilowatt hours outside negative-price hours. Discounted at 5 per cent over 20 years that is 46 euros per kilowatt, a sixth to a fifth of the extra cost. Converted to every kilowatt hour generated, the tall frame costs 1.8 to 2.3 cents; the surcharge is 0.5 cents. The surcharge alone therefore does not carry a high-mounted plant over a pasture. The reasons for this design lie with the land: the farmer only makes it available with grazing, the municipality only agrees to dual use, or the grassland would not be admissible for an ordinary park at all.

For vertical rows the extra cost according to Fraunhofer ISE is small and the revenue per kilowatt higher. In return there is no surcharge today. The land requirement is four times that of an ordinary park. Here the lease decides.

What is established for sheep, cattle and laying hens, and what is open?

Practice with sheep is established, and for cattle the benefit of shade. Open are, for cattle, the results of the German trial plants and, for laying hens, the classification under the EEG.

Sheep: proven as maintenance, rarely the reason for agrivoltaics

Sheep do not need a special design, but they need clean workmanship. The Bavarian State Research Centre for Agriculture gives a lower module edge of at least 80 centimetres for commercial breeds, everywhere on the site including hollows. Cables must be laid out of reach or protected, because sheep gnaw at them and get caught in them. As a grazing fee the same publication gives 150 to 400 euros per hectare as an industry figure, at least 300 euros from the shepherds' point of view and 801 to 855 euros according to a calculation by KTBL. The figures date from 2010 to 2014; we have not found more recent official values. In an ordinary park, 300 to 855 euros per hectare correspond to 0.30 to 0.86 euros per kilowatt and year, that is 0.6 to 1.6 per cent of the annual revenue in our calculation.

Whether lambs grow worse under modules was measured by Oregon State University over two years. The pasture under the modules produced 38 per cent less herbage. Liveweight gain per hectare remained comparable because the forage was of higher quality.

Cattle: shade is documented, loads on the frame

Cattle place higher demands on the frame than sheep. DIN SPEC 91492 requires that the supporting structure is protected against mechanical damage, for example from rubbing with horns. The animals must also be able to move upright under the plant. The trial plants of the agrivoltaics model region Baden-Württemberg on permanent grassland comprise, besides a ground-level reference plant, two vertical systems and one high-mounted tracking plant; two sites are grazed by cattle. The project had not published results on forage yield and animal behaviour by November 2026.

The benefit of shade is documented. In 2019 the University of Minnesota compared dairy cows on pasture with and without the shade of a solar plant. In the afternoon the cows in the shade breathed more slowly (66 instead of 78 breaths per minute) and had a lower body temperature; there was no difference in milk yield. The trial ran with 24 cows and a plant of 30 kilowatts. It is an indication, not proof for large parks.

Laying hens: permitted in the range, a special case under the EEG

With laying hens two areas of law meet. Egg marketing law has allowed solar panels in the open-air run since November 2023 if the competent authority approves, animal welfare is maintained and the hens can move freely (Annex II of Delegated Regulation (EU) 2023/2465). The run must be mainly covered with vegetation, and no more than 2,500 hens per hectare are permitted. Bavaria derives from this that, seen from above, no more than 49 per cent of the run may be covered by modules. It recommends a minimum height of 55 centimetres.

The EEG is the second hurdle. A hen run is a special solar installation on grassland only if the land is permanent grassland and continues to be farmed as such. A run newly laid out on arable land does not meet this on our reading of the determination: the switch from arable land to grassland is excluded; for the arable category the cultivation of crops is missing. Then there is the sward. Hens scratch away the vegetation near the house; where no grass stands permanently, proving grassland farming becomes difficult. A project with laying hens can therefore be an ordinary solar park under the EEG even if it is presented as agrivoltaics. The information memorandum should name the site category of the award.

What the modules do for the animals is being studied by Nürtingen-Geislingen University at two farms with a good megawatt each. Fraunhofer ISE names range behaviour, the distribution of the hens under the plant and the consequences for the sward as open questions. The project ran until the end of 2025; we had not found a published final report by November 2026. Housing orders during avian influenza are regulated: under the EU regulation the eggs may continue to be marketed as free-range during such a restriction. For the EEG, the wording of the determination looks at the farming of the grassland over three years, not at the individual day in the run.

How much agrivoltaics on grassland is awarded?

Little, with a rising trend. The Bundesnetzagentur shows the site type of every bid in its tender statistics, including a separate column for special solar installations on permanent grassland. We evaluated it for all eleven bid dates in which this type appears. From March 2023 to July 2026, 322 megawatts were bid and 137 megawatts awarded, an award rate of 42 per cent. That is 0.6 per cent of all awards on those dates.

YearBidAwardedShare
202357.614.20.27 %
2024103.123.20.35 %
202594.360.10.83 %
2026 to July66.739.00.88 %
Total321.6136.50.58 %
Own evaluation of the Bundesnetzagentur tender statistics for first-segment solar (sheet Übersicht_Flächentyp, column besondere Solaranlage Dauergrünland, status 18.08.2026), in megawatts, share of all awards on the respective dates. Three bid dates each in 2023 to 2025, two so far in 2026. The column does not separate grazing from mowing. Awarded capacity is not built capacity.

For comparison: agrivoltaics on arable land reached 978 megawatts of awards across all dates in the statistics, on permanent crops 214 megawatts (see Agrivoltaics over orchards from an investor's perspective: support, cost per hectare and what the trial plants show). Whether animals graze on the grassland or it is mown cannot be seen from the statistics. At 250 to 600 kilowatts per hectare, 137 megawatts correspond to around 230 to 550 hectares.

What does it cost if the evidence is missing?

Under current law the entire market premium, under the EEG 2027 draft the surcharge. If the expert confirmation is not supplied, the reference value falls by 2.5 cents per kilowatt hour (§ 54 (3) EEG). The consequence ceases for the future if the evidence for the previous year is supplied in the following year. Retroactively it ceases for periods for which it is supplied later.

How much that costs depends on the market value. The reduction lowers the reference value, not the exchange revenue. If the reduced value lies below the annual market value, the market premium falls to zero; the operator cannot lose more than that.

CaseLoss per kWpLoss per ha
2027 draft, 2025 market value€3.7€2,230
Today, market value 3.0 ct€17.0€10,230
Today, 2025 market value€5.8€3,490
Own calculation (scripts/tierhaltung-pv-model.mjs) for the high-mounted plant with 600 kWp per hectare and a reference value of 5.29 ct/kWh (4.79 ct plus 0.5 ct surcharge). Today: reduction of 2.5 ct under § 54 (3) EEG 2023; draft: 0.5 ct under § 54 (2) of the government draft. Annual solar market value 2025: 4.508 ct/kWh; 3.0 ct is a sensitivity assumption.

At 2025 market values the market premium of the high-mounted plant is 5.8 euros per kilowatt and year, a good 10 per cent of the revenue of 55.5 euros. It is lost entirely, because the reduced reference value of 2.79 cents lies below the annual market value of 4.51 cents. If the market value falls, the premium grows and with it the possible loss, up to a maximum of 2.5 cents per remunerated kilowatt hour. That is just under half of a reference value of 5.29 cents. Why the market value of solar power is under pressure is explained in Solar market value: why solar power is worth less and less on the exchange.

The evidence itself is not demanding. The risk is that the operator does not hold it in their own hands alone. If the farm gives up livestock and no successor is found, the farming that the expert is supposed to confirm is missing. The determination allows the switch from grazing to mowing. If the livestock farmer drops out, another farm can therefore mow the land and use the forage, provided the design allows it. Between closely spaced rows or under low modules that cannot be taken for granted.

What must the contract with the livestock farmer regulate?

Above all who answers for damage and what happens if the livestock farmer drops out. The model contract of the state agricultural institutes for sheep grazing shows how the burdens are usually distributed: the shepherd is liable within the scope of their farm liability insurance, beyond that only for intent and gross negligence, capped at one annual grazing fee. They are not meant to be responsible for badly laid cables. Damage from gnawed cables therefore falls largely on the operator and their insurance. A contract with the livestock farmer should regulate at least five points.

  • Liability and insurance: does the plant's insurance expressly cover animal bites and damage by grazing animals? Which liability cover does the livestock farmer evidence?
  • Continuation: duty to farm over the support period, notice period for giving up the farm, right of the operator to appoint another farmer.
  • Evidence: who commissions and pays for the expert confirmation every three years? Which documents does the livestock farmer supply, such as photographs, field record and payment records?
  • Access and operation: times for maintenance and module cleaning, moving the animals out, water supply, fences.
  • Payment: does the operator pay a grazing fee, does the livestock farmer pay a lease, or does no money change hands? That shows whether the livestock is a service or farming in its own right.

Which policies a solar park needs and what they exclude is set out in Insuring a solar park or battery storage asset: which policies belong to a direct investment, and who holds them.

What does the EEG 2027 draft change?

It keeps the surcharge of 0.5 cents, opens it to vertical plants and lowers the reduction for missing evidence. The government draft of 7 September 2026 (Bundestag printed paper 21/7867) provides in § 38a that the reference value for special solar installations on arable land, permanent crops and grassland rises by 0.5 cents if they are mounted at least 2.10 metres high; for exclusively vertically oriented plants 0.80 metres are sufficient. The same is to apply to small plants outside the tender (§ 48 (1b)). The quota for special solar installations, which was never applied, is deleted. The reduction for missing evidence falls to 0.5 cents (§ 54 (2) of the draft).

For vertical pasture plants that would be a noticeable change: in our calculation their revenue rises by 4.1 euros to 70.2 euros per kilowatt and year. The draft contains no rule of its own for livestock and no reference to DIN SPEC 91492. The other changes are described in EEG 2027: what the refinancing contribution means for a solar park direct investment.

What applies to tax and farm subsidies?

For the investor the livestock changes nothing in tax terms. The solar plant is a commercial business; the animals belong to the farmer, and their yields are the farmer's income. The investment deduction (IAB) and special depreciation under § 7g EStG are available for the movable parts of the plant if the conditions are met (see Investitionsabzugsbetrag: all §7g EStG requirements, and who can use it).

For the livestock farmer, farm subsidies matter. Under § 12 (4) no. 6 of the German CAP direct payments ordinance (GAPDZV), land with solar plants counts as used for non-agricultural purposes unless the farm proves that the plant is agrivoltaics: the land must still be workable with usual methods and machinery and may shrink by no more than 15 per cent under DIN SPEC 91434 (§ 12 (5)). An ordinary solar park with sheep does not usually meet this. Under planning law, an agrivoltaics plant on grassland at the farm is privileged in the outer zone up to 25,000 square metres of ground area, one plant per farmstead (§ 35 (1) no. 9 BauGB); larger ones need a development plan.

Which questions should investors ask about a solar park with animals?

  • In which site category did the plant receive its award: as an ordinary ground-mounted plant or as a special solar installation on permanent grassland under § 37 (1) no. 3 (c) EEG?
  • Was the land permanent grassland throughout the five years before commissioning? How is that evidenced?
  • Which surcharge does the model assume? For vertical and ground-level plants there is none under current law.
  • How many kilowatts stand per hectare? Which lease per kilowatt results from that?
  • Which extra costs of the frame compared with a ground-mounted plant are disclosed?
  • Who prepares and pays for the expert confirmation every three years? What is the livestock farmer contractually obliged to do?
  • What happens if the livestock farmer gives up: can the land between and under the modules be mown?
  • Are cables and frame protected against biting and rubbing? Does the insurance cover damage by animals?
  • For laying hens: has the competent authority approved solar panels in the run? How much of the run is covered?

General checkpoints for any provider are set out in How to tell a trustworthy provider of energy direct investments.

How we assess concepts with livestock

We do not currently offer agrivoltaics with livestock. If such a project came to us, we would first clarify the site category of the award and have the grassland status of the last five years evidenced. We model the surcharge as a separate revenue line, with one case with and one without it. We calculate the lease per kilowatt, because only then does it become visible what the lower density costs. We read the contract with the livestock farmer as carefully as the grid connection, because the evidence depends on it. We also check whether the land can be farmed without animals.

We follow new designs even before we offer them. For rewetted peatland and floating plants this is set out in Peatland PV and floating PV as a direct investment: support, EEG 2027 and the evidence the revenue depends on, for orchards in Agrivoltaics over orchards from an investor's perspective: support, cost per hectare and what the trial plants show. Once the German trials on cattle and laying hens are published, we will update this article.


Frequently asked questions

What is agrivoltaics with livestock?

A solar plant on land where farm animals continue to be kept, for example cattle or sheep on pasture or laying hens in an open-air run. Under the German EEG it is a special solar installation if it stands on permanent grassland and grassland farming continues (§ 37 (1) no. 3 (c)). The technical requirements for the interaction of animal and plant are described in DIN SPEC 91492 of June 2024.

Is a solar park with sheep grazing an agrivoltaics plant?

As a rule, no. Grazing there is vegetation management in an ordinary ground-mounted plant. The EEG names it as one of five nature conservation criteria (§ 37 (1a) no. 2). A park is agrivoltaics within the meaning of the EEG only if it was awarded as a special solar installation on permanent grassland and farming is confirmed by an expert every three years.

What support is there for agrivoltaics on grassland in Germany?

The award value from the ordinary tender and, for high-mounted plants from 2.10 metres of clearance, a surcharge of 0.5 cents per kilowatt hour if the award is made in the years 2026 to 2028. Vertical and ground-level plants receive no surcharge today. The EEG 2027 draft provides 0.5 cents for vertical plants from 0.80 metres as well.

May solar modules stand in the range of free-range hens?

Yes, with the approval of the competent authority. The EU marketing standards for eggs have allowed solar panels in the open-air run since November 2023 if animal welfare is maintained and the hens can move freely. The run must be mainly covered with vegetation. Bavaria therefore limits coverage to 49 per cent of the run. Whether the plant counts as agrivoltaics under the EEG is a separate question and depends on permanent grassland.

What does DIN SPEC 91492 regulate?

Requirements for agrivoltaics plants with livestock: two categories (from 2.10 metres of clearance, and ground-level or vertical), no more than 15 per cent loss of land, at least 85 per cent of the stocking of a reference area, protection of the animals from the plant and of the plant from the animals, plus a joint use concept by farmer and operator. The EEG does not refer to it but to the older DIN SPEC 91434.

How much capacity fits on a hectare of pasture with solar modules?

Less than on an ordinary ground-mounted site. Fraunhofer ISE assumes around 1,000 kilowatts per hectare for an ordinary park, 600 kilowatts for high-mounted plants over arable land, 300 kilowatts for permanent grassland farmed between the rows and 250 kilowatts for vertical modules. In our calculation a hectare thus earns 63 per cent (high-mounted) and 31 per cent (vertical) of the electricity revenue of an ordinary park.

What happens if the farmer gives up livestock?

Support as a special solar installation depends on the farming of the grassland, not on a particular species. The Bundesnetzagentur's determination allows the switch from grazing to mowing. If the land is no longer farmed at all, the evidence is missing and the reference value falls today by 2.5 cents per kilowatt hour until the evidence is supplied again.

Is agrivoltaics with livestock worthwhile for investors?

Not through the surcharge. In our calculation the tall frame costs 221 to 284 euros more per kilowatt than for a ground-mounted plant; discounted, the surcharge is worth 46 euros per kilowatt. Such a project stacks up if the lease per kilowatt fits the lower density and the land could not be obtained otherwise. No return promises can be derived from this.

Sources

  1. § 37 EEG 2023, bids for first-segment solar plants (para. 1 no. 3 (c): permanent grassland; para. 1a no. 2: maintenance concept with mowing or strip grazing)
  2. § 48 EEG 2023, solar plants (para. 1 sentence 1 no. 5 (c))
  3. § 54 EEG 2023, reduction of the payment entitlement (para. 3: missing evidence, 2.5 cents)
  4. § 85c EEG 2023, determination on special solar installations
  5. § 101 EEG 2023, state aid approval reservation
  6. Bundesnetzagentur, determination on special solar installations on grassland and peat soils of 1 July 2023, ref. 4.08.01.01/1#4
  7. Bundesnetzagentur, special solar installations: requirements and determinations
  8. Bundesnetzagentur, tender for first-segment solar plants, bid date 1 December 2026 (notes on the Solarpaket I, maximum value)
  9. Bundesnetzagentur, statistics of the tenders for first-segment solar plants (sheet Übersicht_Flächentyp)
  10. Bundestag printed paper 20/2580, committee recommendation on the EEG 2023 (§ 38b (1) sentence 2: surcharge for horizontally mounted special solar installations)
  11. Bundestag printed paper 21/7867, government draft of the EEG 2027 (§ 38a, § 48 (1b), § 54 (2))
  12. DIN SPEC 91492:2024-06, agrivoltaic systems, requirements for livestock farming
  13. DIN SPEC 91434:2021-05, agrivoltaic systems, requirements for primary agricultural use
  14. Commission Delegated Regulation (EU) 2023/2465, marketing standards for eggs (Annex II no. 1: open-air run, solar panels, stocking density)
  15. Bavarian State Research Centre for Agriculture (LfL), notes and recommendations on free-range laying hen husbandry combined with photovoltaic plants, status 28.11.2023
  16. Bavarian State Research Centre for Agriculture (LfL), grazing of photovoltaic plants with sheep, LfL-Information, 2nd edition April 2019
  17. Fraunhofer ISE, Agri-Photovoltaik: Chance für Landwirtschaft und Energiewende, guideline, 4th edition June 2025 (pp. 11, 27, 31, 45)
  18. Fraunhofer ISE, Aktuelle Fakten zur Photovoltaik in Deutschland (density of vertical modules)
  19. Energy and climate protection agency of Rhineland-Palatinate, information paper Agri-PV part 1, technical and economic facts, status 26.01.2026
  20. Agrivoltaics model region Baden-Württemberg, sub-project combining photovoltaics and free-range laying hens
  21. Agrivoltaics model region Baden-Württemberg, sub-project agrivoltaics on permanent grassland
  22. Sharpe, Heins, Buchanan, Reese: Evaluation of solar photovoltaic systems to shade cows in a pasture-based dairy herd, Journal of Dairy Science 104 (2021), pp. 2794 to 2806
  23. Andrew, Higgins, Smallman, Graham, Ates: Herbage Yield, Lamb Growth and Foraging Behavior in Agrivoltaic Production System, Frontiers in Sustainable Food Systems 5 (2021)
  24. § 12 German CAP direct payments ordinance (paras. 4 no. 6 and 5: agrivoltaics plant)
  25. § 35 BauGB, building in the outer zone (para. 1 no. 9)
  26. European Commission, JRC, PVGIS 5.3 (hourly profiles, weather year 2023)
  27. Bundesnetzagentur, SMARD, market data (day-ahead prices 2025)
  28. netztransparenz.de, market value overview (annual solar market value 2025)

Read on

Articles that follow thematically.

Personal first conversation

Less reading: a short call.

30 minutes, free and without obligation. We understand your tax situation and show which project structures fit you, or whether today is (not yet) the right moment.

Learn more